At a glance
Three to look at first
How the plan scores
Tap any bar to see the reasoning. The green marker shows roughly where a good, proportionate construction phase plan for a job this size would sit. Nobody needs a 10 everywhere.
What's already working
Walking the job
Findings
Each one opens to show what I found, why it matters, something to think about, and what I'd like to see. Tap a bubble on the chart to jump straight to it.
The evidence list
Every line here is something the plan says happens.
Tick each one off as it's shown. If most of these are in place, things are in a much better state than the paperwork suggests. Anything that isn't can either be put in place or taken out of the plan. Ticks are saved in this browser only.
| # | What the plan says | Page | What I'd like to see | How far back | Finding | Seen |
|---|
Not in the plan, but good to have
Section by section
How each section of the plan's risk register rates its own risks. Tap a bar for my view. Sections copied from a bigger site, and the High risks left as they are, are the giveaways.
Which kind of control does it lean on?
The best controls take the hazard away or engineer it out. Training and PPE come last, because they depend on people getting it right every time. Counting control words across the document shows it leans heavily on the bottom two. These counts are indicative, not exact.
Next steps
A rough order to tackle things in, tied to the stages of the job. Each line says who would normally pick it up.
Eight questions
What the law says
The wording behind the findings, with a plain-English note under each. These are extracts, so the full text on legislation.gov.uk is the one to rely on.